Home About Services Areas Projects Blog Contact 07472 424 226

How Long Does a House Renovation Take?

Renovation AdvicePublished June 2026Updated July 20268 min read

Key Takeaways

  • A full house renovation takes 3 to 6 months on site, and 5 to 10 months from first drawing to handover.
  • A kitchen takes 3 to 5 weeks, a bathroom 10 to 15 working days.
  • Extensions take 10 to 16 weeks on site, loft conversions 6 to 10 weeks.
  • Design, consents and lead times add 6 to 16 weeks before anyone arrives, and that is the part people leave out.
  • A party structure notice is two months and a householder planning decision around 8 weeks (gov.uk and MHCLG, 2026). Both gate the start date.
  • Staying in the house through the works typically adds 30 to 50% to the programme on services work.

One of the first questions homeowners ask is how long it will all take, and the honest answer is that the build is rarely the long part. Design, consents and lead times routinely take as long again. Here are realistic durations for London projects in 2026, what has to happen before site, and what actually causes the overruns.

How long does each type of renovation take?

A full house renovation takes 3 to 6 months on site, a single-storey extension 10 to 16 weeks, a loft conversion 6 to 10 weeks, a kitchen 3 to 5 weeks and a bathroom 10 to 15 working days. The column that surprises people is the first one: the lead-in before anyone turns up.

ProjectDesign and consents, before siteTime on siteRealistic total
Bathroom refurbishment2 to 4 weeks for design and orders10 to 15 working days6 to 10 weeks
Kitchen renovation4 to 8 weeks, longer for bespoke3 to 5 weeks2 to 3 months
Kitchen with a structural opening6 to 10 weeks, party wall and building control6 to 8 weeks4 to 5 months
Loft conversion8 to 16 weeks6 to 10 weeks4 to 7 months
Single-storey rear extension12 to 20 weeks10 to 16 weeks6 to 9 months
Full house renovation6 to 16 weeks3 to 6 months5 to 10 months
Site durations from GS Renovation programmes for London properties, 2026, cross-checked against Checkatrade and Federation of Master Builders guidance, 2026. Consent periods from MHCLG planning statistics for England, 2026, and the Party Wall etc. Act 1996 explanatory booklet, gov.uk, 2026. Totals assume the consent and build phases run consecutively, which they usually do on a domestic job.

Two things move these figures more than anything else. A structural opening adds a party wall notice period, an engineer, a building control application and steel fabrication, which is why the same kitchen goes from 3 weeks to 8. And a mansard, a trussed roof or a pre-1919 property that has never been opened up all sit at the longer end of every band.

What has to happen before work starts?

Between six and sixteen weeks of design, consents and ordering, running roughly in this order. None of it is optional and none of it can be shortened by paying more.

  • Survey and design, 2 to 4 weeks. A measured survey, then existing and proposed drawings.
  • Planning, around 8 weeks from validation. A householder application costs £548 from 1 April 2026. Councils in England decided 93% of householder applications within 8 weeks or an agreed extension in the quarter to March 2026, so treat 8 weeks as the target rather than the guarantee. Many projects need no application at all under permitted development.
  • Structural calculations and building control, 1 to 3 weeks. A full plans application can take up to 8 weeks, though it is usually faster. See Building Regulations explained.
  • Party wall notices, one or two months. Two months for a party structure notice, one month for a line of junction or adjacent excavation notice, plus 14 days for the neighbour to reply and a few weeks more if they dissent. This is the single most commonly underestimated item in a London programme. See the Party Wall Act explained.
  • Builder availability. Good contractors are booked weeks or months ahead. A start date is only a start date once it is in a contract.
Planning fee per MHCLG planning fees indexation, 1 April 2026. Decision performance per MHCLG, Planning applications in England: January to March 2026. Party wall notice periods per the Party Wall etc. Act 1996 explanatory booklet, gov.uk, 2026.

Which materials have the longest lead times?

Windows, bespoke joinery and stone, all of which are made to order rather than picked off a shelf. These are the items that stop a site, because a site with nothing left to do still costs money.

ItemTypical lead timeOrder it by
Standard kitchen units4 to 8 weeksStart of first fix
Bespoke or handmade cabinetry10 to 16 weeksBefore strip out
Stone or quartz worktop1 to 2 weeks after templatingTemplated once units are fitted and level
Made-to-measure timber sash windows8 to 12 weeks from surveyBefore structural work starts
Aluminium or steel-look glazed doors8 to 12 weeksBefore the opening is formed
Fabricated structural steel1 to 3 weeksOn approval of the calculations
Sanitaryware and brassware2 to 6 weeksBefore first fix, so pipework matches
Engineered timber flooring2 to 4 weeks, plus acclimatisationBefore plastering
Lead times are indicative, from GS Renovation supplier experience at London rates, 2026; timber sash window lead time per London sash window specialists, 2025 to 2026. Confirm current lead times with your own supplier at the point of order, because they move with demand.

Why does a London renovation take longer?

Access, consents and the age of the housing stock, in that order. The same specification in a suburban detached house genuinely does run faster than in a Victorian terrace.

  • Everything goes through the front door. A terraced house with no side access means every tonne of waste out and every pallet of materials in is carried by hand, which adds days rather than hours across a whole-house job.
  • Borough permissions run on their own clocks. A skip needs a highway permit, pavement scaffold a licence, and a parking bay suspension is charged per bay per day and has to be applied for in advance.
  • Working hours are restricted. Most London boroughs allow noisy work roughly 08:00 to 18:00 on weekdays and 08:00 to 13:00 on Saturdays, with nothing on Sundays or bank holidays. A site with a hard 18:00 stop cannot make up a lost afternoon in the evening.
  • Attached properties mean party wall notices. Terraces and semis nearly always trigger the Act on structural work.
  • Pre-1919 stock hides more. Lath and plaster, lime mortar, notched joists and drains that are not where the plan says all surface in week one, which is exactly what the contingency is for.

What causes delays, and how do you avoid them?

Late decisions and late orders cause more lost weeks than anything on site does. A builder can absorb a surprise in the fabric. Nobody can absorb a ten week lead time discovered in week nine.

  • Finalise the design and every material choice before work starts. Tiles, sanitaryware, brassware, flooring, ironmongery and paint colours all belong in the specification, not in a conversation on site.
  • Order long lead-time items early, using the table above.
  • Keep a contingency of 10 to 15%, 20% in a pre-1919 house. A surprise with money behind it costs days. A surprise without costs weeks while it is argued about.
  • Follow the order of works. Rework is the most expensive kind of delay because you pay for the same work twice.
  • Use one coordinated team so the plasterer arrives the day after first fix passes rather than the following week.
  • Decide whether you are staying. Living in the house through services work typically adds 30 to 50% to that part of the programme. See living in your home during a renovation.

Then hold the last fortnight properly: snagging, certificates and handover are a stage in their own right, not something that happens on the final afternoon. For a realistic, dated programme for your project, whether that is a whole-house renovation or an extension, contact us or call 07472 424 226.

AS
Abdelaaziz Saaid is the founder and director of GS Renovation Ltd. With over 30 years delivering structural, renovation and extension projects across London, these guides reflect his hands-on site experience and current UK building practice.

FAQ

Frequently Asked Questions

How long does a full house renovation take?

A full house renovation in London usually takes 3 to 6 months on site for a standard property, and longer where there are extensions or significant structural works. Design, permissions and material lead times add several weeks before work begins, so plan the whole journey, not just the build.

How long does a kitchen or bathroom take?

A kitchen renovation takes around 3 to 5 weeks, longer if structural work is involved. A full bathroom refurbishment takes around 10 to 15 working days. Wet rooms and rooms needing layout changes sit at the longer end.

How long does an extension or loft take?

A single-storey extension takes 10 to 16 weeks on site, and a loft conversion 6 to 10 weeks, both preceded by design and any planning permission. Double-storey extensions and mansards take longer.

What causes renovation delays?

The most common causes are decisions made late by the homeowner, materials ordered too late, unexpected issues uncovered in older properties, and poor coordination between trades. Planning thoroughly, deciding promptly and ordering early prevent most delays.

Can I speed up a renovation?

Yes, by finalising the design and all material choices before work starts, ordering long lead-time items early, keeping a contingency for surprises, and using one coordinated team so trades are sequenced efficiently. Rushing the build itself rarely helps and often causes mistakes.

Planning a Project in London?

Get a free, no-obligation quote from GS Renovation. Over 30 years of hands-on experience across all 32 London boroughs.

Get Your Free Quote